Close Light Download image Dark Share Stock exchange is momentarily closed
Download image

Coal phaseout at Stuttgart-Münster

Climate-neutral by 2035 – based on this promise, EnBW is committed to playing its part in mitigating climate change in line with the 2015 Paris Agreement. For EnBW, this partly means continuing to systematically expand renewable energy capacity, while also pursuing its aim of phasing out the use of coal in the medium term and the use of fossil fuels as an energy source in the long term. EnBW is one step closer to achieving this aim with the construction of a new gas turbine plant for generating electricity and heat based on more climate-friendly natural gas at its Stuttgart-Münster site. The fuel switch to more climate-friendly natural gas is just a bridging technology on the way to energy generation using green gases such as hydrogen produced from renewable sources.

Download image

Project diary

This is where we inform you about important events and milestones relating to the planning and construction of a gas turbine plant on the Stuttgart-Münster site. You will find the latest information here on the timetable for the planning and permit process as well as the progress of the construction work.

June 2024
Receipt of the 3rd partial license
May 2024
Delivery and lifting of the waste heat boiler chimney elements
April 2024
Official commissioning of the large-scale heat pump
Delivery and assembly of the gas turbines
March 2024
Submission of the 3rd partial license
February 2024
Early start of construction of the black start battery system received
January 2024
Delivery of the hot water boilers and associated chimneys
November 2023
Start of commissioning of the large-scale heat pump
September/October 2023
Delivery of the waste heat boilers for the gas turbines
June 2023
Receipt of the second partial license
31 March 2023
Groundbreaking ceremony for the new gas turbine plant and the large-scale heat pump
January 2023
Preliminary permit decision received and first partial approval
October 2022
Stuttgart Regional Council meeting to discuss the project
22 March 2022
Investment decision taken by EnBW’s Supervisory Board
7 February 2022
Permit application submitted
21 July 2021
Project presented to Bad Cannstatt council committee
23 April 2021
Scoping meeting0In complex planning processes, a scoping meeting is held by the authority overseeing the process (in this case Stuttgart Regional Council). With the involvement of public agencies and specialist authorities, the meeting is used to formally determine the subject, scope and methodology of the regional impact and environmental impact studies as well as the content of the application documents that need to be drawn up.
20 April 2021
Project presented to Münster council committee
13 April 2021
Virtual information event for the public
12 April 2021
Information event for professional associations and citizens’ initiatives
less more