Building and operating a grid stabilization plant
To ensure grid stability and security of supply, additional generation facilities ("special grid-related equipment in accordance with Section 11 (3) EnWG") are required as part of the Energiewende. EnBW is currently constructing such a grid stability facility at its power plant site in Marbach am Neckar. Following completion of the approval process in accordance with the Federal Immission Control Act (BImSchG) in July 2020, the plant is currently under construction. Due to delays, commissioning is targeted for 2024.
Project diary
This is where we inform you about important events and milestones relating to the planning and construction of the grid stabilization plant on the Marbach site. You will find the latest information here on the timetable for the planning and approval process as well as the progress of the construction work.
Project timeline
29 November 2018
|
Citizen information
Energy and technology park at Marbach power plant Reinhold-Würth-Straße 4 / Am alten Kraftwerk, first floor |
December 2018
|
Scoping meeting* for Stuttgart Regional Council
|
August 2019
|
Contract awarded to EnBW upon completion of the tendering process
|
3rd quarter 2019
|
Application submitted for approval in line with immission control regulations
|
3rd quarter 2019
|
Start of work on existing 110 kV plant at the site
|
July 2020
|
Approval granted and start of construction
|
December 2021
|
Approval change
|
April 2022
|
Grid connection completed
|
July 2022
|
Commissioning of demineralization plant
|
Q4 2023
|
Work starts on commissioning the grid stabilization plant
|
Q3 2024
|
Commercial operation of the grid stabilization plant
|
* In complex planning processes, a scoping meeting is held by the authority overseeing the process (in this case Stuttgart Regional Council). With the involvement of public agencies and specialist authorities, the meeting is used to formally determine the subject, scope and methodology of the regional impact and environmental impact studies as well as the content of the application documents that need to be drawn up.
Construction diary
Contact
Events
No further events are currently planned.